We have a lot going on. Here is an update on the 1835 Town Hall projects:

Roofing

  • The roof is fully sheathed with new shingles and flashing
  • Steel bracing has been installed at Bay 3 and 4
  • We are waiting on steel reinforcement pieces to be fabricated for Bay 1 and 2
  • We are preparing a plan and budget for the MCFF grant. We are working to have that by November 25th
  • Vareika and Tom Rutherford are both working to get heat into the building. Contractors are busy, but they continue to apply pressure. Heat is essential for some of the finish wok and painting.


Lift

  • We are waiting for delivery of Lift from Garaventa – due by first week of December

 

Septic

  • Cabco engineering has determined the elevations for the septic at the 1835 and at the forced main off Waushacum Ave at the fire house system. Thanks to the efforts of the DPW last week.
  • Cabco is proceeding to prepare the details for the easements we will need for 27 Main Street and 2 Pine Street.
  • Easement language is expected in December
  • Final plans are due in January 2019 with estimate for FY 2020 capital request

Sprinkler

  • We are working to obtain design and costs for sprinkler system for possible inclusion in FY 2020 capital request

Budget

  • Below is a worksheet (also attached) of the finances for the project to date.